Battery lines simulated against sudden production changes

Find out how the lines would respond to sudden changes in the production programme, stoppages included.

Plan view of a simulation model with AGVs, illustrative SIMULATION · SCHEMATIC ST. 01 ST. 02 ST. 03 ST. 04 QUEUE BRIDGE
Illustrative image
Client
Confidential client
01

Context

At a battery plant, the question was whether the lines could absorb the production changes requested from one day to the next, some of them very sudden.

02

Challenge

  • Production programme changes from one day to the next
03

What we did

We simulated the lines numerically with a Python model: it takes the production inputs, includes stoppages and returns the line's response at each iteration.

  1. Numerical line model

    Production inputs, stoppages and results, iteration by iteration.

A similar project? Let’s talk.

You hear back from the team that does that work: CYP ENGY, CYP DATA or CYP SIRE.

Request sent.

We have received your message.

The request could not be sent.

Write to us at info@cypcore.com.

Tell us what you need